Federal grants to Wood County Regional Airport Authority
Wood County Regional Airport Authority in Bowling Green, Ohio received $5.7 million in federal grants from fiscal 2021 to 2025, across 11 awards. Its largest program was Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with $5.7 million. In fiscal 2025 it was awarded $328,989.
From USAspending.gov award records, updated November 7, 2026.
- Grants, FY 2021 to 2025$5.7 million
- Awards11
- Awarded in FY 2025$328,989
- Largest award$4.8 million
By year
| Fiscal year | Awards | Amount |
|---|---|---|
| FY 2021 | 2 | $24,097 |
| FY 2022 | 4 | $333,218 |
| FY 2023 | 0 | $0 |
| FY 2024 | 3 | $5.0 million |
| FY 2025 | 2 | $328,989 |
Programs that fund Wood County Regional Airport Authority
| Program | Awards | Amount |
|---|---|---|
| Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | 11 | $5.7 million |
Awarding agencies
| Agency | Awards | Amount |
|---|---|---|
| Department of Transportation | 11 | $5.7 million |
Largest awards
| Award | Program | First action | Amount |
|---|---|---|---|
| Purpose: extend/expand runway. Activities to be performed/expected outcomes: this project extends and expands runway 18/36 an additional 572 feet in length and 10 feet in width to bring the airport into conformity with current standards. This project extends and expands runway 18/36 an additional 57 | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 28, 2024 | $4.8 million |
| Purpose: extend/expand runway. Activities to be performed/expected outcomes: this project extends and expands runway 18/36 an additional 572 feet in length and 10 feet in width to bring the airport into conformity with current standards. This grant funds phase 5, which installs precision approach pa | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 26, 2024 | $216,152 |
| Purpose: construct apron; construct/expand hangar; construct taxilane. Activities to be performed/expected outcomes: this project constructs a new 12,300 square foot sponsor-owned hangar for aircraft storage to assist the airport to be as self-sustaining as possible by generating revenue. This proje | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | September 8, 2025 | $178,989 |
| Purpose: conduct airport related environmental assessment/plan/study. Activities to be performed/expected outcomes: this project conducts an environmental assessment to evaluate any potential environmental impacts related to the proposed runway 18/36 extension. . Intended beneficiary: this grant wil | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 29, 2022 | $157,500 |
| Purpose: reconstruct runway lighting; rehabilitate runway. Activities to be performed/expected outcomes: this project reconstructs existing runway 10/28 lighting that has reached the end of its useful life. This project rehabilitates 4,201 feet of existing paved runway 10/28 to maintain the structur | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 25, 2025 | $150,000 |
| Purpose: acquire snow removal equipment; seal runway pavement surface/pavement joints. Activities to be performed/expected outcomes: this project acquires new carrier vehicle with plow equipment to enhance the airport's ability to clear the airfield during adverse weather conditions. . This project | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | September 7, 2022 | $137,988 |
| Purpose: american rescue plan act awarded as economic assistance to eligible U.S. Airports and eligible concessions at those airports to prevent, prepare for, and respond to the COVID-19 pandemic. Activities to be performed/expected outcomes: this grant provides economic relief funds for costs relat | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | February 18, 2022 | $32,000 |
| Improve existing airport | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | June 17, 2021 | $13,000 |
| Improve existing airport | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | November 12, 2020 | $11,097 |
| Improve existing airport | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | July 30, 2024 | $6,356 |
Questions people ask
How much federal grant money does Wood County Regional Airport Authority get?
$5.7 million in 11 grant awards from fiscal 2021 to 2025, as obligations reported to USAspending.gov.
Which agency gives Wood County Regional Airport Authority the most?
The Department of Transportation, with $5.7 million in 11 awards.
What is Wood County Regional Airport Authority's largest federal grant?
$4.8 million under Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with its first action in the period on August 28, 2024. That counts only the money obligated in fiscal 2021 to 2025.
Other grant recipients in Bowling Green
Largest federal grant recipients in Ohio · Federal grants in Ohio