Federal grants to Columbia Marion County Airport
Columbia Marion County Airport in Columbia, Mississippi received $3.9 million in federal grants from fiscal 2021 to 2025, across 7 awards. Its largest program was Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with $3.9 million. In fiscal 2025 it was awarded $1.3 million.
From USAspending.gov award records, updated November 7, 2026.
- Grants, FY 2021 to 2025$3.9 million
- Awards7
- Awarded in FY 2025$1.3 million
- Largest award$2.3 million
By year
| Fiscal year | Awards | Amount |
|---|---|---|
| FY 2021 | 2 | $163,000 |
| FY 2022 | 2 | $106,220 |
| FY 2023 | 1 | $2.3 million |
| FY 2024 | 0 | $0 |
| FY 2025 | 2 | $1.3 million |
Programs that fund Columbia Marion County Airport
| Program | Awards | Amount |
|---|---|---|
| Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | 7 | $3.9 million |
Awarding agencies
| Agency | Awards | Amount |
|---|---|---|
| Department of Transportation | 7 | $3.9 million |
Largest awards
| Award | Program | First action | Amount |
|---|---|---|---|
| Purpose: reconstruct taxiway. Activities to be performed/expected outcomes: this project reconstructs 3,000 feet of the existing southwest parallel taxiway pavement that has reached the end of its useful life. This grant funds the final phase, which consists of reconstruction of 3,000 feet. Intended | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 8, 2023 | $2.3 million |
| Purpose: extend/expand taxilane; expand apron. Activities to be performed/expected outcomes: this project expands the existing terminal apron an additional 15,000 square yards to accommodate more based aircraft and allow access to a broader fleet mix. This project extends the existing apron taxilane | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | July 8, 2025 | $1.1 million |
| Purpose: extend/expand taxilane; expand apron. Activities to be performed/expected outcomes: this project expands the existing terminal apron an additional 15,000 square yards to accommodate more based aircraft and allow access to a broader fleet mix. This project extends the existing apron taxilane | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | July 4, 2025 | $159,000 |
| Improve existing airport | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | February 26, 2021 | $150,000 |
| Purpose: construct apron. Activities to be performed/expected outcomes: this project constructs a 15,000 square yard terminal apron to meet the needs of the existing users of the airport. This grant funds the design phase. Intended beneficiary: this grant will provide federal funding for airports as | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | July 18, 2022 | $74,220 |
| Purpose: american rescue plan act awarded as economic assistance to eligible U.S. Airports and eligible concessions at those airports to prevent, prepare for, and respond to the COVID-19 pandemic. Activities to be performed/expected outcomes: this grant provides economic relief funds for costs relat | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | November 18, 2021 | $32,000 |
| Improve existing airport | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | April 8, 2021 | $13,000 |
Questions people ask
How much federal grant money does Columbia Marion County Airport get?
$3.9 million in 7 grant awards from fiscal 2021 to 2025, as obligations reported to USAspending.gov.
Which agency gives Columbia Marion County Airport the most?
The Department of Transportation, with $3.9 million in 7 awards.
What is Columbia Marion County Airport's largest federal grant?
$2.3 million under Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with its first action in the period on August 8, 2023. That counts only the money obligated in fiscal 2021 to 2025.
Other grant recipients in Columbia
Largest federal grant recipients in Mississippi · Federal grants in Mississippi