DOT - Federal Railroad Administration offered grants of up to $8.2 million to state and local governments. It expected to make one award worth $8.2 million in total. Applications closed on November 21, 2025.
From the official notice on Grants.gov, last changed November 13, 2025. Checked November 7, 2026.
- Award ceiling$8.2 million
- Total funding$8.2 million
- Expected awards1
- Cost sharingRequired
- Funding typeGrant
Key dates
| Posted | October 31, 2025 |
|---|---|
| Deadline | November 21, 2025 |
| Archived by Grants.gov | December 21, 2025 |
Who can apply
This opportunity was open to state and local governments.
- County governments
Is this a realistic fit?
- The notice requires cost sharing or matching funds, so you must contribute part of the project cost.
What the grant funds
This Project is part of a larger effort to restore function to the Great River Railroad that runs from the Port of Rosedale to the Columbus and Greenville Railroad (CAGY) in Metcalf, MS. The larger effort is divided into two Phases. Under this Agreement, the Project will complete environmental review for both phases. Additionally, this Project will complete preliminary engineering, final design, and construction activities for Phase 1 of the larger effort. Under this Agreement, Phase 1 activities will include preliminary engineering, final design, and construction activities to repair the 31 mile railroad to be a functional track for maintenance equipment by replacing ties (approximately one-third of the timber rail ties), repairing 33 grade crossings, installing additional supplemental ballast rock, resurfacing track, repairing 4 timber bridges, replacing 1 timber bridge with culverts, and installing 1 concrete culvert. Phase 2 of the restoration effort is anticipated to include installing approximately 31 miles of new 112–115-pound rail, additional tie replacement, the replacement of 4 bridges, and improvements to sidings (Port of Rosedale spur) in order to restore the track to a full operation. Besides environmental review, this Agreement does not fund activities for Phase 2. Successful completion of the Project will enhance resiliency and redundancy for both the Port of Rosedale and the wider region.
Applying now
This notice no longer takes applications. Agencies often post the same opportunity again under a new number, so check the program's notices on Grants.gov and the similar open grants below.
The notice on Grants.gov keeps its full text and attachments, which is useful for planning a resubmission.
Questions people ask
Is FR-CCD-24-010 still open?
No. It closed on November 21, 2025.
Who can apply for FY24 Port of Rosedale Multimodal Expansion: Great River Railroad Restoration Project?
DOT - Federal Railroad Administration accepted applications from state and local governments.
What is the deadline for FY24 Port of Rosedale Multimodal Expansion: Great River Railroad Restoration Project?
Closed November 21, 2025. Applications are no longer accepted; the program's newer notices are on this page when there are any.
How much funding is available?
Awards of up to $8.2 million each. About $8.2 million in total for one award.