Federal grants to Benedum Airport Authority

Bridgeport, West Virginia · State and local governments · UEI QC4HYKQHU2C5

Benedum Airport Authority in Bridgeport, West Virginia received $40.9 million in federal grants from fiscal 2021 to 2025, across 18 awards. Its largest program was Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with $37.7 million. In fiscal 2025 it was awarded $6.6 million.

From USAspending.gov award records, updated November 7, 2026.

By year

Federal grants to Benedum Airport Authority by fiscal year
Fiscal yearAwardsAmount
FY 20213$1.1 million
FY 20223$3.7 million
FY 20234$19.9 million
FY 20245$9.6 million
FY 20253$6.6 million

An award funded in several years counts in each of them, so yearly awards add up to more than the five-year total.

Programs that fund Benedum Airport Authority

Every program, fiscal 2021 to 2025
ProgramAwardsAmount
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs 20.10617$37.7 million
Economic Adjustment Assistance 11.3071$3.2 million

Awarding agencies

AgencyAwardsAmount
Department of Transportation17$37.7 million
Department of Commerce1$3.2 million

Largest awards

The 10 largest awards by money obligated in fiscal 2021 to 2025
AwardProgramFirst actionAmount
Purpose: construct terminal building. Activities to be performed/expected outcomes: this project constructs a new 52,600 square foot terminal building to increase passenger throughput. . This grant funds the first phase, which consists of design and construction of 38,676 square feet. Intended benef
ASST_NON_35400050522023_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJanuary 25, 2023$15.0 million
The project consists of the construction of four parking lots with a total of approximately 600 parking spaces and appurtenances. The lots are divided into the short-term parking lot, long-term parking lot, employee parking lot and rental car parking lot. All parking areas will have sidewalk access
ASST_NON_ED24PHI0G0432_013 on USAspending
Economic Adjustment AssistanceSeptember 9, 2024$3.2 million
Purpose: construct apron. Activities to be performed/expected outcomes: this project constructs a new 13,555 square yard terminal apron to accommodate more aircraft operations. This grant funds phase 3, which consists of construction of 5,195 square yards. Intended beneficiary: this grant will provi
ASST_NON_35400050602025_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJuly 14, 2025$3.0 million
Purpose: construct taxiway. Activities to be performed/expected outcomes: this project constructs a new 1,110 foot paved taxiway j to bring the airport into conformity with current standards. This grant funds the final phase, which consists of construction. Intended beneficiary: this grant will prov
ASST_NON_35400050562024_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJuly 12, 2024$2.5 million
Purpose: construct taxiway; construct apron. Activities to be performed/expected outcomes: this project constructs a 1,200 foot partial parallel taxiway i to eliminate the need for aircraft to back-taxi on the runway. This project constructs a new 13,555 square yard terminal apron to accommodate inc
ASST_NON_35400050512022_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJuly 7, 2022$2.5 million
Purpose: construct terminal access road. Activities to be performed/expected outcomes: this project constructs a new 3,950 foot access road to the main terminal to accommodate more vehicular traffic exclusively serving the airport. This grant funds phase 1, which consists of construction of 2,550 li
ASST_NON_35400050572024_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJuly 26, 2024$2.5 million
Purpose: construct apron. Activities to be performed/expected outcomes: this project constructs a new 13,555 square yard terminal apron to accommodate more aircraft operations. This grant funds the final phase, which consists of construction of 4,120 square yards. Intended beneficiary: this grant wi
ASST_NON_35400050612025_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJune 26, 2025$2.4 million
Purpose: construct terminal building. Activities to be performed/expected outcomes: this project constructs a new 52,600 square foot terminal building to increase passenger throughput. . This grant funds the third phase, which consists of construction of 8,090 square feet. Intended beneficiary: this
ASST_NON_35400050542023_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJanuary 27, 2023$2.2 million
Purpose: construct terminal building. Activities to be performed/expected outcomes: this project constructs a new 52,600 square foot terminal building to increase passenger throughput. . This grant funds the second phase, which consists of construction of 5,834 square feet. Intended beneficiary: thi
ASST_NON_35400050532023_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsMarch 27, 2023$2.1 million
Purpose: reconstruct runway lighting. Activities to be performed/expected outcomes: this project reconstructs existing runway 3-21 lighting that has reached the end of its useful life. Intended beneficiary: this grant will provide federal funding for airports associated with clarksburg, west virgini
ASST_NON_35400050622025_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJuly 21, 2025$1.2 million

Amounts are net obligations: money committed, minus any amounts taken back. They are not payments. See how our data works.

Questions people ask

How much federal grant money does Benedum Airport Authority get?

$40.9 million in 18 grant awards from fiscal 2021 to 2025, as obligations reported to USAspending.gov.

Which agency gives Benedum Airport Authority the most?

The Department of Transportation, with $37.7 million in 17 awards. The Department of Commerce follow.

What is Benedum Airport Authority's largest federal grant?

$15.0 million under Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with its first action in the period on January 25, 2023. That counts only the money obligated in fiscal 2021 to 2025.

Which federal programs fund Benedum Airport Authority?

Its largest are Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs and Economic Adjustment Assistance.

Other grant recipients in Bridgeport

Largest federal grant recipients in West Virginia · Federal grants in West Virginia