Federal grants to City of Miller
City of Miller in Miller, South Dakota received $1.8 million in federal grants from fiscal 2021 to 2025, across 6 awards. Its largest program was Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with $1.8 million. In fiscal 2025 it was awarded $944,300.
From USAspending.gov award records, updated November 7, 2026.
- Grants, FY 2021 to 2025$1.8 million
- Awards6
- Awarded in FY 2025$944,300
- Largest award$863,550
By year
| Fiscal year | Awards | Amount |
|---|---|---|
| FY 2021 | 3 | $773,777 |
| FY 2022 | 1 | $22,222 |
| FY 2023 | 0 | -$49,033 |
| FY 2024 | 1 | $81,000 |
| FY 2025 | 2 | $944,300 |
Programs that fund City of Miller
| Program | Awards | Amount |
|---|---|---|
| Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | 6 | $1.8 million |
Awarding agencies
| Agency | Awards | Amount |
|---|---|---|
| Department of Transportation | 6 | $1.8 million |
Largest awards
| Award | Program | First action | Amount |
|---|---|---|---|
| Purpose: reconstruct airport rotating beacon; reconstruct taxiway; reconstruct terminal access road. Activities to be performed/expected outcomes: this project reconstructs 300 feet of the existing taxiway a pavement that has reached the end of its useful life. This project reconstructs 600 feet of | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 6, 2025 | $863,550 |
| Purpose: reconstruct taxilane; extend taxilane. This grant includes funding by the american rescue plan act of 2021 to increase the federal share to 100 percent for the airport improvement program (AIP). Activities to be performed/expected outcomes: this project extends the hangar taxilane to 900 fe | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | July 13, 2021 | $735,395 |
| Purpose: reconstruct access road; reconstruct taxiway. Activities to be performed/expected outcomes: this project reconstructs 300 feet of the existing taxiway a pavement that has reached the end of its useful life. This project reconstructs 750 feet of the existing access road that has reached the | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | July 2, 2024 | $81,000 |
| Purpose: install weather reporting equipment. Activities to be performed/expected outcomes: this project acquires and installs a new automated weather observing system type iii-p to provide site-specific weather information. This grant funds phase 1, which consists of design. Intended beneficiary: t | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | September 3, 2025 | $80,750 |
| Purpose: american rescue plan act awarded as economic assistance to eligible U.S. Airports and eligible concessions at those airports to prevent, prepare for, and respond to the COVID-19 pandemic. Activities to be performed/expected outcomes: this grant provides economic relief funds for costs relat | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 20, 2021 | $22,000 |
| Purpose: coronavirus relief and response supplemental appropriations act funds awarded as economic relief to eligible U.S. Airports and eligible concessions at those airports to prevent, prepare for, and respond to the COVID-19 pandemic. Activities to be performed/expected outcomes: this grant provi | Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs | August 12, 2021 | $9,000 |
Questions people ask
How much federal grant money does City of Miller get?
$1.8 million in 6 grant awards from fiscal 2021 to 2025, as obligations reported to USAspending.gov.
Which agency gives City of Miller the most?
The Department of Transportation, with $1.8 million in 6 awards.
What is City of Miller's largest federal grant?
$863,550 under Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with its first action in the period on August 6, 2025. That counts only the money obligated in fiscal 2021 to 2025.
Other grant recipients in Miller
Largest federal grant recipients in South Dakota · Federal grants in South Dakota