Well Told Grants

Federal grant recipients / Minnesota

Federal grants to Bemidji Regional Airport Authority Commission

Bemidji, Minnesota · State and local governments · UEI G477JEH7ZTC2

Bemidji Regional Airport Authority Commission in Bemidji, Minnesota received $16.7 million in federal grants from fiscal 2021 to 2025, across 13 awards. Its largest program was Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with $16.7 million. In fiscal 2025 it was awarded $4.3 million.

From USAspending.gov award records, updated November 7, 2026.

By year

Federal grants to Bemidji Regional Airport Authority Commission by fiscal year
Fiscal yearAwardsAmount
FY 20214$1.9 million
FY 20223$2.1 million
FY 20232$6.5 million
FY 20242$2.0 million
FY 20252$4.3 million

An award funded in several years counts in each of them, so yearly awards add up to more than the five-year total.

Programs that fund Bemidji Regional Airport Authority Commission

Every program, fiscal 2021 to 2025
ProgramAwardsAmount
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs 20.10613$16.7 million

Awarding agencies

AgencyAwardsAmount
Department of Transportation13$16.7 million

Largest awards

The 10 largest awards by money obligated in fiscal 2021 to 2025
AwardProgramFirst actionAmount
Purpose: strengthen runway; rehabilitate runway. Activities to be performed/expected outcomes: this project rehabilitates 7,004 feet of runway 13/31 to maintain the structural integrity of the pavement. This project strengthens 7,004 feet of runway 13/31 to accommodate a heavier class of aircraft an
ASST_NON_32700100452023_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJune 29, 2023$4.7 million
Purpose: rehabilitate taxiway; update exhibit a airport property inventory map; realign taxiway. Activities to be performed/expected outcomes: this project realigns existing paved taxiway a by 90 degrees to bring the airport into conformity with current standards. This project rehabilitates 8,297 fe
ASST_NON_32700100502025_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsSeptember 18, 2025$3.8 million
Purpose: improve/modify/rehabilitate service road; construct taxilane. Activities to be performed/expected outcomes: this project constructs a 450 foot taxilane to connect an existing parking area to a hangar area. . This project improves an existing on-airport roadway around the air operations area
ASST_NON_32700100462023_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsAugust 10, 2023$1.8 million
Purpose: american rescue plan act awarded as economic assistance to eligible U.S. Airports and eligible concessions at those airports to prevent, prepare for, and respond to the COVID-19 pandemic. Activities to be performed/expected outcomes: this grant provides economic relief funds for costs relat
ASST_NON_32700100422022_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJanuary 26, 2022$1.2 million
Purpose: construct/expand fuel farm; reseal taxilane pavement. Activities to be performed/expected outcomes: this project constructs a new pump fuel facility at a non hub primary airport by adding one self service pump and associated apron pavement for a new fuel type to assist the airport to be as
ASST_NON_32700100472024_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsAugust 27, 2024$1.1 million
Improve existing airport
ASST_NON_32700100402021_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsMarch 24, 2021$1.0 million
Purpose: seal apron pavement surface/pavement joints; acquire snow removal equipment; rehabilitate runway; obstruction marking/lighting/removal [non-hazard]. Activities to be performed/expected outcomes: this project acquires a new carrier vehicle with plow equipment to keep the airport serviceable
ASST_NON_32700100442022_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsAugust 11, 2022$942,981
Purpose: reseal taxilane pavement; rehabilitate taxiway; reseal taxiway pavement; reseal apron pavement; reconstruct snow removal equipment; realign taxiway. Activities to be performed/expected outcomes: this project realigns existing paved taxiway a connector by 45 degrees to bring the airport into
ASST_NON_32700100482024_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsAugust 20, 2024$921,334
Improve existing airport
ASST_NON_32700100392021_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJune 17, 2021$812,078
Purpose: construct/expand fuel farm. Activities to be performed/expected outcomes: this project constructs a new pump fuel facility at a non hub primary airport by adding one self service pump and associated apron pavement for a new fuel type to assist the airport to be as self-sustaining as possibl
ASST_NON_32700100492025_069 on USAspending
Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports ProgramsJuly 16, 2025$462,531

Amounts are net obligations: money committed, minus any amounts taken back. They are not payments. See how our data works.

Questions people ask

How much federal grant money does Bemidji Regional Airport Authority Commission get?

$16.7 million in 13 grant awards from fiscal 2021 to 2025, as obligations reported to USAspending.gov.

Which agency gives Bemidji Regional Airport Authority Commission the most?

The Department of Transportation, with $16.7 million in 13 awards.

What is Bemidji Regional Airport Authority Commission's largest federal grant?

$4.7 million under Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs, with its first action in the period on June 29, 2023. That counts only the money obligated in fiscal 2021 to 2025.

Other grant recipients in Bemidji

Largest federal grant recipients in Minnesota · Federal grants in Minnesota